Valeriu Iftime – pagina principală

Botoșani County, Romania · for investors

Această pagină în română

Romania's north-eastern corner is getting connected. Here is what that means for you.

Botoșani County lies on the European Union's border with Ukraine and the Republic of Moldova and has 392,821 residents. For decades, investors passed it by: no motorway, no gas in the north, no 400 kV transmission grid. The road, gas and power infrastructure that changes this is approved, in preparation or under construction, with the dates taken from the documents. This page makes the case, with figures taken from public documents.

This page lists all major investments in the county, not only those of Botoșani County Council: national agencies and state companies (CNAIR, Transgaz, Transelectrica, Romanian Waters), municipalities, the water utility and private companies. Each one shows who is behind it.

Investment in the county, all sources

RON 3.15 bn · ≈ €629 m

Projects

71, in 56 of the 78 localities

Under construction now

22 projects · RON 936.4 m

County Council, since October 2024

40 contracts, decisions and tenders · 15 handovers and acceptances

Why Botoșani: six reasons

  • 01

    A location that is becoming an asset

    Botoșani is Romania's north-eastern corner, on the European Union's external border with both Ukraine and the Republic of Moldova. A county road being rebuilt with EU funds leads to the Rădăuți-Prut crossing into Moldova, a second crossing operates at Stânca–Costești, and the Racovăț–Diakivți crossing into Ukraine, currently open to passenger traffic only, is to be upgraded for freight. As Moldova moves towards EU membership and Ukraine rebuilds, the county sits on the route.

  • 02

    Power on a scale the county has never had

    The new 400 kV Suceava–Bălți transmission line crosses eleven of the county's communes. The county's first 400/110 kV substation, at Bălușeni, is scheduled by the transmission system operator for 2030; in February 2026 the county council approved the partnership protocol with the commune and the two grid companies. Eurowind Energy holds grid-connection approval for 1,188 MW of wind capacity across nine localities in the north: eight communes and the town of Darabani. For the first time, energy-intensive industry becomes possible here.

  • 03

    Gas, at last

    Săveni, Darabani and Ștefănești have never had natural gas. Three pipelines, declared of national importance by the Government in July 2026, will bring it there; the transmission operator put the pipe materials out to tender in September 2026. Fibre-optic cable will be laid along the same route.

  • 04

    The motorway link

    The A7 motorway, the north–south backbone of north-eastern Romania, will run just west of the county. The Botoșani–Suceava expressway will connect to it at Salcea, the Botoșani ring road is under construction, and the Dorohoi bypass has an approved feasibility study. A county that was once a detour is becoming a destination.

  • 05

    Land and industrial parks

    In 2026 the county council and five towns set up a county development company for industrial parks. The first sites are at Săveni, Ștefănești, Dorohoi and Darabani, along the route of the new gas pipelines, and six zones have been identified across the county: land where the utilities are on their way.

  • 06

    An administration that speaks the language of business

    The president ran an engineering group for three decades before entering public office. The council has shifted money from running costs to development, and every project funded under Romania's EU Recovery and Resilience Plan was closed out ahead of the deadline. Investors deal with a single point of contact: the president's office, which brings mayors, utility companies and permitting authorities to the same table.

Where to invest

Click a locality to select it in the form. The deeper the gold, the more works are under way there.

BotoșaniBuceceaDarabaniDorohoiFlămânziSăveniȘtefănești
  • Industrial park being prepared
  • Along the new gas pipelines
  • 400/110 kV substation
  • Border crossing
  • Expressway and ring road
  • Eurowind wind farms
  • works under way

Tell us what you are looking for

A few lines are enough. You will receive a confirmation with a reference number and, if you request it, the county report. The office replies in English or Romanian.

What you would like from us

Who you will be dealing with

Valeriu Iftime has been President of Botoșani County Council since October 2024. Before entering public office, he spent three decades building and running an engineering group in energy and district heating, with projects across Romania, and he chaired the county's Chamber of Commerce. He came to the council with one stated economic priority: without jobs the county has no future, and without roads, gas and water there are no jobs. The county's 2025 budget allocated about 40% to development, and all of the county's projects under Romania's EU Recovery and Resilience Plan were closed out ahead of the deadline.

What is being built

The projects that matter most to a company considering the county. Status and value are taken from the project pages (in Romanian), which link to the source documents.

  • Planned· led by CNAIR, the national roads company, in partnership with Botoșani and Suceava county councils

    Botoșani–Suceava expressway, linking the county to the A7 motorway

    Four lanes over 19.9 km, designed for 120 km/h: the missing link between the county and Romania's motorway network.

    Project page and documents (in Romanian) →
  • Under construction· led by the Botoșani Metropolitan Area intercommunity development association

    Botoșani ring road, phase 1

    Takes heavy traffic out of the city and gives direct access to industrial land. The works contract was signed in July 2026, with 24 months to complete.

    Source document (in Romanian) →
  • In tenderRON 284.1 m · ≈ €57 m· led by Transgaz SA

    Three natural-gas pipelines for the north of the county

    The first gas supply for Săveni, Darabani and Ștefănești, declared a project of national importance. The pipe materials were put out to tender in September 2026.

    Project page and documents (in Romanian) →
  • Planned· led by Transelectrica and Delgaz Grid

    400/110 kV substation at Bălușeni, the county's first 400 kV (extra-high-voltage) node

    Today the grid stops at 110 kV, so large energy projects cannot connect. A substation on the new Suceava–Bălți line changes that.

    Project page and documents (in Romanian) →
  • Planned· led by Eurowind Energy

    Eurowind Energy's 1,188 MW wind portfolio: nine wind farms in the north

    A private investment of over one billion euros by a Danish developer, with grid-connection approval from the transmission system operator.

    Source document (in Romanian) →
  • Under constructionRON 339.7 m · ≈ €68 m· led by Botoșani County Council

    County road DJ 282 to the Moldovan border at Rădăuți-Prut

    48.8 km being rebuilt with EU funds, from Hănești through Săveni to the Rădăuți-Prut border crossing into the Republic of Moldova.

    Project page and documents (in Romanian) →
  • PlannedRON 837 m · ≈ €167 m· led by Nova Apaserv, the regional water utility, with the Aqua Botoșani intercommunity association

    Regional water and wastewater programme

    EU-funded water networks and treatment plants reaching over 120 towns and villages: the largest water project ever prepared in the county, financing contract still pending.

    Project page and documents (in Romanian) →
  • PlannedRON 164.5 m · ≈ €33 m· led by Botoșani County Council

    Hănești–George Enescu drinking-water main

    A 43 km drinking-water main from Hănești to George Enescu, serving six communes and the town of Săveni. The design is complete and updated; funding is being sought.

    Project page and documents (in Romanian) →
  • Under construction · 70%RON 78.4 m · ≈ €16 m· led by Botoșani County Council

    County road DJ 293, Mileanca–Coțușca

    15 km of county road being rebuilt in the north of the county, with four bridges, paid for entirely from the county budget.

    Project page and documents (in Romanian) →
  • Under constructionRON 8.5 m · ≈ €2 m· led by Botoșani County Council

    County-owned 1 MW solar park at Bucecea

    The county's own solar park of almost 1 MW at Bucecea, supplying power to the County Hospital and funded by the Modernisation Fund.

    Project page and documents (in Romanian) →
  • PlannedRON 448 m · ≈ €90 m· led by CNAIR

    Dorohoi bypass

    12.75 km around the county's second-largest town, with the feasibility study approved by the Ministry of Transport in June 2026.

    Source document (in Romanian) →

Timeline

  1. 2026

    Ring road works under way; gas pipeline materials out to tender; regional water programme at the financing stage; industrial-park company up and running.

  2. 2027

    Gas pipeline construction (the county council president's estimate, not a contractual date set by Transgaz); expressway feasibility study and technical design; first new water and sewerage works.

  3. 2028

    Ring road phase 1 due for completion (24 months from August 2026).

  4. 2029–2031

    Water programme completed; 400/110 kV substation in operation (2030, according to the transmission operator); wind farms built in phases.

Dates are taken from contracts, government decisions and the operators' published plans, as cited on the project pages. Where a project has no firm date, we do not give one.

The portfolio by sector

SectorProjectsValue
Water and sewerage14RON 1.16 bn · ≈ €233 m
Roads and bridges12RON 1.05 bn · ≈ €210 m
Energy and environment5RON 426 m · ≈ €85 m
Health16RON 216.4 m · ≈ €43 m
Culture and tourism10RON 159.1 m · ≈ €32 m
Education5RON 72.9 m · ≈ €15 m
Administration6RON 44.1 m · ≈ €9 m
Social services3RON 13 m · ≈ €3 m

Euro amounts are indicative, at about RON 5 to the euro. Values are those in the public documents cited on each project page.

How to get started

  1. 1

    Write to us

    Use the form below or send an e-mail. Tell us your sector, how much land you need, your power, gas and water requirements, and your timeline.

  2. 2

    We match your needs to what is available

    Which industrial park or site fits, which utilities are there today and what is coming when, and which mayor and which operator need to be involved.

  3. 3

    Meet, then visit

    A meeting with the president's office, followed by a site visit with the mayors and the utility companies. Every figure on this site comes from a public document, so you can check it before you travel.

Office of the President, Botoșani County Council

Piața Revoluției 1-3, 710236 Botoșani, Romania

Phone: +40 231 514 712

E-mail: [email protected]

County Council website: www.cjbotosani.ro

Write in English or Romanian. Site visits and meetings with mayors and utility companies are arranged through the office.

County report for investors (PDF)

Infrastructure, zones, flagship projects, timeline and contacts in a few pages, ready to forward or print for a meeting. Generated from the same data as this website.

Download PDF

Personal website of Valeriu Iftime; not the official website of Botoșani County Council. All project data, with sources, is openly available: CSV and JSON.

Share:FacebookWhatsApp